Journey to the Handover – Episode 02

Update

26th-February-2026

Bayfancy Residence Construction Update

📌 Current Construction Progress

• 🧱 Masonry Works: 100% Completed
 • 🏠 15th Floor Wall Plastering: 100% Completed
 • 🏠 14th Floor Wall Plastering: 50% Completed
 • 🛡️ Roofing & External Waterproofing: 100% Completed
 • ✨ Show Apartment: 70% Completed
 • 🌫️ External Wall Plastering: 30% Completed

🚧 Ongoing Operations

• 🌫️ External wall plastering works are actively progressing
 • 🏠 Internal wall plastering works are ongoing on the 14th floor.

This episode highlights the steady and disciplined progress of Bayfancy Residence as we advance through critical structural completion and finishing milestones. With masonry, roofing, and waterproofing fully completed, the project has successfully transitioned into its refined finishing phase.

Wall plastering is progressing systematically across upper floors, while the show apartment continues to take shape, now 70% complete. Each completed element reflects coordinated planning, engineering precision, and consistent quality supervision.

Through our Journey to Handover series, we remain committed to transparency and structured progress reporting. Every milestone achieved brings us closer to timely handover, reinforcing our promise to deliver homes built to premium standards and lasting value.