Construction Update - 10th of December

Update

10th-December-2025

Bayfancy Residence Construction Update 

📅 10th December 2025

📌 Current Construction Progress

• 🧱 Masonry works of the 14th Floor completed

• 🪨 Ground Floor plastering works 90 percent completed

•  Marking for the MEP location of the show apartment completed

• ⚡ Initial MEP works in the model house completed

🚧 Ongoing Operations

• 🧱 Masonry works on the 15th Floor are actively progressing

• 🪨 Plastering works on the 8th Floor ongoing

Overview

The progress unfolding across Bayfancy Residence reflects a construction approach grounded in precision, engineering discipline, and long term durability. Each phase is carried out with careful planning to ensure a well balanced living environment that supports energy efficiency, privacy, and the long lasting comfort expected in a modern luxury residence. As teams move across the site, the workmanship and attention to detail continue to shape the project into a place designed for both quality living and enduring value.

Key Progress

The masonry works on the 14th floor have now been fully completed, reflecting consistent progress in the masonry phase and reinforcing the precision of the building’s overall finish. On the ground floor, plastering has reached 90 percent completion, revealing cleaner lines and a more polished architectural profile.
 
 

14th Floor Completed Masonry Works

The marking for the MEP locations of the show apartment was completed with a high level of accuracy and coordination, setting out every point in advance to ensure flawless alignment during installation. This step highlights the project’s commitment to precision and quality, confirming that all future utilities will follow a clearly defined and well planned system. The clarity and exactness of this marking work stand as an important assurance of long-term performance, safety, and overall living comfort within the show apartment.

Following this, the initial MEP installations in the model house have been successfully completed. These early electrical and plumbing integrations create the foundation for the smart, functional, and reliable systems that will enhance the overall residential experience within Bayfancy.

Ongoing Work

Masonry works have now progressed to the 15th floor, maintaining steady progress in the masonry schedule and ensuring quality and consistency across all floors. Meanwhile, plastering teams are currently working on the 8th floor, gradually moving upward as each level reaches the required readiness.

Looking Ahead

As these layers of progress continue to build, the project edges closer to the next milestone. With finishing works, masonry progress, and interior preparations moving in harmony, the project continues with strong engineering discipline. Every step is guided by durable construction standards, energy-efficient planning, and layouts designed to offer residents a higher sense of privacy and long-term comfort. With scientific management, efficient construction coordination, and the dedication of our skilled project teams, we remain fully aligned with our commitment to hand over each new home to our valued owners by December 31, 2026, as planned.