Bayfancy Residence – 14F Slab completed

Update

19th-August-2025

🏢 Bayfancy Residence – 14F Slab completed
📆 *19th August 2025*

📌 Current Construction Progress:
• 🏗️ Completion of 14F slab concrete pouring
• 🧱 The masonry works on the 5th floor has been completed

🔄 Ongoing Operations:
• 🔩 Reinforcement and formwork installation for the 15th floor slab in progress
• 🧰 The masonry works on the 6th floor has been 20% completed

🛡️ Construction Safety Protection Systems – Safety Nets & Hoist Protection
🔒 Our dual-protection system (safety nets + hoist guards) ensures full-process safety for high-rise construction, edge work, and vertical transport.

✅ Safety Net Protection
• 🏗 Scaffolding built to high standards with secure spacing and fastening
• 🛡 Comprehensive edge guards, overhead nets, and toe boards for 360° protection
• 📋 Standardized material selection & maintenance with dedicated inspections

✅ Hoist Protection
• 🔐 Enhanced Safety: 1.2m reinforced railings + dual brakes + smart overload protection
• 🔍 Rigorous Checks: Daily triple inspections + monthly load tests + quarterly professional audits
• 🎯 Precision Operation: Guide rail accuracy (≤3mm/m) with real-time load/vibration monitoring

🌟 These systems act as "3D Safety Guardians", combining fall prevention (nets) and vertical transport protection (hoists) for personnel and materials.

💎 Bayfancy Residence remains steadfast in its mission to "create personalized smart luxury living" meticulously crafting benchmark-quality residences.

👷 Bayfancy team consistently dedicated to refining residential environments and crafting superior lifestyles for our residents.

Room 202, Infinity Hub,

Lot 11629 Mirihi Magu,

Hulhumalé Phase 1, 23000, Maldives



Copyright © Bayfancy PTE Ltd 2025

All rights reserved