Bayfancy Residence – 12F Slab completed

Update

30th-July-2025

🏢 Bayfancy Residence – 12F Slab completed
📅 30th July 2025

📈 Current Construction Progress:
• ✅ Completion of 12F slab concrete pouring
• 🧱 The construction of internal partition walls on the 3rd floor has been completed

⚙️ Ongoing Operations:
• 🔨 Reinforcement and formwork installation for the 13th floor slab in progress
• � The construction of interior partition walls on the 4th floor has been 50% completed

🏗️ Architectural Technique: Waterproof & Moisture-Resistant Construction
In high-humidity areas such as 🍳 kitchens, 🚽 bathrooms, and 🌿 balconies, a 20cm reinforced concrete base wall is systematically installed to:
• 🛡️ Block moisture penetration
• 💧 Prevent liquid leakage
• 🏋️ Enhance structural stability

Functioning as an impermeable barrier, this concrete foundation effectively safeguards walls against water damage and moisture erosion, significantly extending the building's service life.

✨ Bayfancy Residence remains steadfast in its mission to "create personalized smart luxury living" meticulously crafting benchmark-quality residences.

👷 Bayfancy team consistently dedicated to refining residential environments and crafting superior lifestyles for our residents.