Bayfancy Residence – 10F Slab completed

Update

29th-June-2025

✨ Bayfancy Residence – 10F Slab completed
📅 29th June 2025

🏗️ Current Construction Progress:
• Completion of 10F slab concrete pouring
• The construction of internal partition walls on the first floor has been completed

👷 Ongoing Operations:
• Reinforcement and formwork installation for the 11th floor slab in progress
• The construction of interior partition walls on the 2nd floor has been 70% completed

🏆 Bayfancy Residence remains steadfast in its mission to "create personalized smart luxury living", meticulously crafting benchmark-quality residences.

📈 The Bayfancy team is consistently dedicated to refining residential environments and crafting superior lifestyles for our residents.