Bayfancy Residence – 8F Slab completed

Update

10th-June-2025

🏗️ Bayfancy Residence – 8F Slab completed
🗓️ 10th June 2025

📋 Current Construction Progress:
✅ Completion of 8F slab concrete pouring
☑️ The internal partition walls on the G floor have been completed

🔧 Ongoing Operations:
🛠️ Reinforcement and formwork installation for the 9th floor slab in progress
🧱 The construction of interior partition walls on the 2nd floor is currently in progress

💎 Bayfancy Residence remains steadfast in its mission to "create personalized smart luxury living" meticulously crafting benchmark-quality residences.

🌟 Bayfancy team consistently dedicated to refining residential environments and crafting superior lifestyles for our residents.